WATER PROOFING SYSTEMS FOR THE SWIMMING POOL AND SEWERAGE TREATMENT PLANTS

 Water Proofing System for swimming pool & sewerage treatment plants comprises of following :

1.  R.C.C. Admixture                             : Super Plasticizer

2.  Plaster Admixture                             : Integral Water Proofer

3.  Cement Slurry Admixture                 : Hycrete RJ - 608

4.  Rubberised Instant Water Proofer    : Water Proof Coating

5.  Insta Plug Mortar                              : For fixing Grouting nozzles

6.  Rapid Grout                                      : For Grouting Cement Slurry

7.  Strextra NSG -110                            : For sealing Grouting holes after saturating grouting

8.  Tile Fix #1                                         : For fixing tiles

9.  Tile Joint Sealer                                : Tile Joints

10. Corrosion protect                             : For higher corrosion resistance needed in case of sewerage

                                                                plants  

11. Epoxy Coatings                                : For coating M.S. portions against corrosion

1. For all P.C.C & R.C.C. concreting, use super plasticizer      Considering 6" R.C.C, M 20 concrete 

    dosage 200ml per bag of cement.                                         Cost per Sq.ft. for addition Rs.0.75

 

2. After casting bottom P.C.C., apply two coats of R.W.I.P.

    Allow 24 hrs to dry, then place reinforements and cast bottom    R.C.C.

 

3. For all external/Internal plastering use I.W.P. 200ml per        Considering 6" R.C.C., m 20 concrete

     bag of cement.  Cement, sieved fine sand in proportion 1:3.  Cost per Sq.ft. Rs.0.65

 

4. Before casting fresh concrete on earlier concrete cement        Cost per Sq.ft. Rs.0.25

    slurry is spread.  Prepare cement slurry with Hycrete RJ - 608

    to eliminate cold set cracks.         

5. After casting vertical lintels & plastering.  Coat two coats            Cost per Sq.ft. Rs.5.00

     of Rubberised Instant Water Proof Coating, externally.

 

6. Cold set cracks :

    (i) Generally occur at 4" height in vertical lintels.  Since shuttery ply is 8" X 4", hence please note

        "Shuttering - Steps" height which is critical.

    (ii) At vertical junction of two vertical sides.

   (iii) At junction of horizontal and vertical sides, these points are inherently weak spots for seepage. 

         Make holes 1" diameter and 2" deep, fix 1" diameter socket above these holes using Insta Plug 

         Mortar. Grout cement slurry with Rapid Grout.

7.      Use 1" diameter , 5' height, G I pipe, screw pipe on the socket and pour cement slurry using Rapid

      Grout till saturation grouting.  For vertical lintels this procedure must be done after internal and

        external plastering is done, but before coating external surface  with R.I.W.P.

8. After saturation grouting, knock off the sockets, and plug grouting holes with Strextra NSG - 110.

 

9. In case of water treatment plants use Corrosion Protect,            Cost per sq ft Rs. 0.25

   1 kg per bag of cement with I.W.P. for internal plaster. If pure

   cement finish is being provided use 1 kg Corrosion Protect per

   50 kg cement.

 

9A. For Swimming Pools use Tile Fix # 1 for fixing Tile on the        Cost per sq ft Rs. 2.00

      internal surface

10. Seal Tile Joints with Tile Joint Sealer.                                        Cost per sq ft Rs. 0.20